Governor’s VDOT Performance and Financial Audit Identifies $1.45 Billion Available for Projects in 6 Year Transportation Program

Independent Study Produces 50 Recommendations; Criticizes Past VDOT Practices that Delayed Projects and Left Funding Unutilized

***$877 Million Left Unspent over Past Two Fiscal Years***

Post-Audit Action: $800 to $900 Million of Maintenance and Construction Contracts to be Awarded by December 31st

Governor: “Virginia’s transportation infrastructure needs require a comprehensive approach, including greater management efficiency, more innovation and new sources of funding. We must demand better stewardship and utilization of existing funds. That is why I ordered this comprehensive performance and financial audit shortly after I took office, and why the findings are so important. This audit demonstrates that available funding has not been effectively used in the past few years. That is unacceptable. Money has been sitting in the state’s wallet while Virginian’s have been sitting in traffic.”

 RICHMOND – Governor Bob McDonnell released today the results of the independent financial and performance audit of the Virginia Department of Transportation (VDOT) that he ordered shortly after taking office. The audit, conducted by the respected firm of Cherry, Bekaert and Holland, LLP beginning in April 2010, examined VDOT’s operations to identify cost-savings strategies, organizational efficiencies, and performance and operational metrics. Among the top findings: the presence of $1 billion in funding available for transportation projects in the Commonwealth, but not utilized to date.  The governor was joined at the afternoon press conference at the State Capitol by Lieutenant Governor Bill Bolling, Secretary of Transportation Sean Connaughton, VDOT Commissioner Greg Whirley, and a number of members of the General Assembly.

 The full audit is available at: http://www.governor.virginia.gov/tempContent/CBH_Performance_Audit_Report-VDOT.pdf

 A summary of the audit is available at: http://www.governor.virginia.gov/tempContent/VDOT-Performance_Audit_Summary.ppt.

 Among the more than 50 audit findings are:

  • Approximately $1 billion in funding is currently available for VDOT’s maintenance and construction program that has not been used.  This is not new funding, rather it is funding that would result from better leveraging and management of current resources
  • Federal funds should be obligated earlier during the fiscal year to eliminate current delays. Over the past two federal fiscal years, less than 10% of available amounts had been obligated 6 months into the year.
  • Monitoring of inactive projects must be improved to release unused funding for other VDOT projects as soon as possible.  In FFY10, $163 million in federal obligations on inactive projects were released (20% of annual obligation).
  • More closely monitor locally administered safety and regional projects to ensure funding is utilized in a timely and cost effective manner
  • Over $100 million in projects were delayed due to partial funding and other administrative issues found in the audit.
  • Approval should be obtained from the Federal Highway Administration to use the over $400 million in toll credits available to Virginia. Toll credits allow VDOT to use 100% federal funds on a project and eliminates the state match requirement, thus freeing up a like amount of cash.
  • The $524 million federal revenue reserve should be eliminated to better leverage existing resources. Adding back these reserves to the budget will accelerate the planning of projects in the Six-Year Improvement Program
  • Revise cash reserve policies to reduce from a 5.5-month reserve to a 60-day reserve, freeing up $200 million for immediate use on transportation projects

 Speaking about the audit, Governor McDonnell remarked, “Virginia’s transportation infrastructure needs require a comprehensive approach, including greater management efficiency, more innovation and new sources of funding. We must demand better stewardship and utilization of existing funds. That is why I ordered this comprehensive performance and financial audit shortly after I took office, and why the findings are so important. This audit demonstrates that available funding has not been effectively used in the past few years. That is unacceptable. Money has been sitting in the state’s wallet while Virginian’s have been sitting in traffic.  We will move immediately to put this funding to work building roads and reducing congestion statewide. VDOT will award $800 to $900 million in contracts by December 31st, and we will get long overdue construction underway. We will not tolerate inefficiency or mismanagement at VDOT or any other state agency.”

The governor continued, noting, “Our transportation funding challenges, deteriorating pavements, aging bridges and the vital link between transportation and our economic prosperity required us to thoroughly examine VDOT policies and programs to find ways we can better manage Virginia’s highways. This audit provides an objective set of recommendations upon which we can improve the administration of Virginia’s transportation program. It is just one part of the comprehensive approach to transportation that we are taking. Through effective utilization of existing funds, and the procurement of new funding strategies, such as  gaining $500 million or more from the privatization of our ABC stores, we will get traffic moving faster in Virginia.”

Lieutenant Governor Bill Bolling added, “Many of us have been calling for an independent, external audit of VDOT for several years.  We wanted to make certain that VDOT was spending the taxpayers money as efficiently as possible.  While we felt that significant operational inefficiencies existed with the Department, this audit has revealed that the problems were even more serious than we thought.  Fortunately, we have now identified those operational inefficiencies and we are moving to correct them as quickly as possible, and in the process we have freed up significant additional resources to help address Virginia’s highway maintenance and construction needs.  This is a significant step in our ongoing efforts to build a transportation system for the 21st century.”

The money identified in the audit comprises state and federal funds that are available for projects but not currently programmed.

Since 2009, the state had cut approximately $2.8 billion from the Six-Year Program citing falling revenues due to the economic downturn.  Of the identified $1 billion, approximately $614 million can be used to award construction and maintenance contracts within the next 12 months.  The balance of $440 million can be programmed to accelerate projects within the Six-Year Improvement Program.  As one of the largest procurement agencies in the state, spending over $2 billion annually on contractual services, adding these funds into the program will improve our transportation system and the Commonwealth’s economy as a whole.  Citing studies by the Federal Highway Administration and the American Association of State Highway Transportation Officials, the governor recognized how VDOT’s rate of spending can impact the economy and job growth.

“Our transportation program is intended to enhance the mobility and safety of our citizens and businesses. In addition, every $100 million spent on highway construction and maintenance projects adds 3,000 jobs created or supported, $250 million in economic activity and $25 million in revenue for the commonwealth,” McDonnell said.

 The report cites several major contributing factors that led VDOT to its current situation:

  • A change in philosophy in managing maintenance projects beginning in 2006 which ignored the annual aspects of the maintenance budget.
  • Loss of focus on managing the maintenance and construction operation during 18-month agency reorganization
  • The economic downturn which caused VDOT to become extremely and overly hesitant in committing available funds, causing $877 million to remain unspent
  • Burdensome internal processes and financial controls for project development

  Maintenance Spending

 The study found significant opportunities to improve the way VDOT spends its available dollars to maintain Virginia’s 58,000 miles of roadways.

During fiscal year 2009, VDOT had available $1.58 billion for maintenance. However, it spent only $1.23 billion, resulting in it carrying over $348 million. During fiscal year 2010, VDOT had available $1.66 billion for maintenance. However, it spent only $1.13 billion, resulting in it carrying over $529 million. This compares with $8 million carried over at the end of fiscal year 2005.

 “Every penny we have available for transportation should be quickly used for construction, paving, bridge and other maintenance contracts,” said Sean T. Connaughton, Secretary of Transportation. “We cannot begin to address how we fund transportation in the future until we are maximizing the use of transportation revenues we currently receive.”

The audit identified a lack of budget accountability from 2006-2009 within the maintenance program as the primary reason funds were not being spent in a timely fashion.

Project Development and Execution

The audit identified VDOT’s one-size-fits-all approach to project development and execution as a reason many projects are slow to develop. Major interchange projects are managed the same as small turn-lane or repaving projects. It cited burdensome fiscal controls that slowed project development, particularly the practice of developing every maintenance project as though it would be eligible for federal funding. This practice required all projects to undergo the rigorous environmental, funding and design reviews required of federally funded projects, even if they ultimately ended up being paid for by less restricted state funds.

The report suggests VDOT develop a tiered process to manage projects according to their complexity and risk, with corresponding levels of controls.

The report also identified procurement processes that take too long. Recent reviews by VDOT’s own inspector general were referenced, stating that it could take over one year to hire an engineer to design a project. The audit recommends re-evaluating the processes and procedures that slow procurement and focus only on what is legally required.

Funding

Acknowledging that transportation funding is a highly complex process with multiple funding sources and eligibility rules, the audit recommends a more aggressive funding strategy that reduces cash balances, cuts federal reserves and accelerates the obligation of federal funding as soon as it becomes available. It also instructs VDOT to develop consistent processes to monitor inactive projects so that funding does not remain on projects that are not moving forward.

 Reorganization and Staffing Changes

The audit recommends additional analysis to identify processes that can be changed to make the new organizational structure within VDOT work. It also encourages VDOT to quickly hire key staff and implement the functions necessary to make the new organizational structure work.

 VDOT should also develop more robust policies and performance metrics to manage the outsourcing of work that comes with the new organizational structure.

 Next Steps

 “This review confirms many of the financial management concerns we have heard from industry experts and elected officials,” said Connaughton. “It is time for us to take action to address the issues raised and reroute our transportation program to the right path for our future.”

The governor has given Connaughton and VDOT Commissioner Gregory A. Whirley 45 days to develop a full action plan to address the audit findings. The administration has already taken numerous steps to improve accountability, focusing on delivering projects faster and improving how VDOT functions. This includes a new management team and changes in executive management duties and responsibilities.

Governor McDonnell recently appointed Charlie Kilpatrick as VDOT’s Chief Deputy Commissioner and VDOT’s nine district administrators now report to Kilpatrick. He is charged with holding them accountable for maintenance spending, project delivery and emergency response.

A new Chief of Planning and Programming has been established to put more focus on the development of the construction program, and the agency has advertised for a new Chief Financial Officer.  

VDOT will hire new state construction and maintenance engineers to provide clear leadership and to implement the findings of this audit in these areas.

To learn more about VDOT or these audit findings, visit www.VirginiaDOT.org.

  ###